Online Civil Engineering Test - Construction Management Test

Instruction:

  • This is a FREE online test. Beware of scammers who ask for money to attend this test.
  • Total number of questions: 20.
  • Time allotted: 30 minutes.
  • Each question carries 1 mark; there are no negative marks.
  • DO NOT refresh the page.
  • All the best!

Marks : 2/20


Total number of questions
20
Number of answered questions
0
Number of unanswered questions
20
Test Review : View answers and explanation for this test.

1.
Military organisation is known as
line organisation
line and staff organisation
functional organisation
none of these.
Your Answer: Option
(Not Answered)
Correct Answer: Option

2.
The salient feature of functional organisation is
strict adherence to specifications
separation of planning and design part
each individual maintains functional efficiency
work is properly planned and distributed
all the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

3.
Site order book is used for recording
instructions by the executive engineers
construction measurements
issue of store equipments
names of the casual labour.
Your Answer: Option
(Not Answered)
Correct Answer: Option

4.
Bar charts are suitable for
minor works
major works
large projects
all the Above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

5.
Critical path method
is an improvement upon bar chart method
provides a realistic approach to daily problems
avoids delays which are very common in bar charts
was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

6.
Completion of an activity on CPM network diagram, is generally known
Event
Node
Connector
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

7.
Pick up the incorrect statement from the following:
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Each activity consumes a given time.
Your Answer: Option
(Not Answered)
Correct Answer: Option

8.
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
EF = ES + D
LS = LF - D
LF = LS + D
D = EF - ES
all the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

9.
The difference between the time avail-to do a job and the time required to do the job, is known as
event
float
duration
constraint.
Your Answer: Option
(Not Answered)
Correct Answer: Option

10.
Which one of the following represents an activity
excavation for foundation
curing of concrete
setting of question paper
preparation of breakfast
all the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

11.
Critical path lies along the activities having total float
positive
negative
zero
same.
Your Answer: Option
(Not Answered)
Correct Answer: Option

12.
The time which results in the least, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Your Answer: Option
(Not Answered)
Correct Answer: Option

13.
Pick up the PERT event from the following:
Digging of foundation started
Digging of foundation completed
Laying of concrete started
Laying of concrete completed
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

14.
Railway projects are treated as
light construction
heavy construction
industrial construction
none of these.
Your Answer: Option
(Not Answered)
Correct Answer: Option

15.
Power stations are generally treated as
light construction
heavy construction
industrial construction
electrical construction.
Your Answer: Option
(Not Answered)
Correct Answer: Option

16.
A goiden rule for the procurement of construction stones, suggests
100% at the site
67% at the site and 33% under procurement
50% at the site and 50% under procurement
33% at the site and 67% under procurement
none of these.
Your Answer: Option
(Not Answered)
Correct Answer: Option

17.
Pick up the incorrect statement from the following:
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these,
Your Answer: Option
(Not Answered)
Correct Answer: Option

18.
Which one of the following represents an event ?
concrete cured
fixing of door
plastering of walls
selecting sites
all the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

19.
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

20.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
Your Answer: Option
(Not Answered)
Correct Answer: Option

*** END OF THE TEST ***