The difference between the time avail-to do a job and the time required to do the job, is known as

[A]. event
[B]. float
[C]. duration
[D]. constraint.

Answer: Option B

Explanation:

No answer description available for this question.

Dhaffod said: (Nov 2, 2018)  
Float =Time availed - Time Required.

Float shows the time within which you can delay an activity without affecting the overall duration of a project.

Y R said: (Jun 7, 2019)  
Thanks all for explaining.