Civil Engineering - Construction Management
Exercise :: Construction Management - Section 1
26. |
The difference between the time avail-to do a job and the time required to do the job, is known as |
A. |
event | B. |
float | C. |
duration | D. |
constraint. |
Answer: Option B
Explanation:
|
27. |
The object of technical planning, is |
A. |
preparation of specifications | B. |
preparation of estimates | C. |
initiating the procurement action of resources | D. |
taking remedial action for likely bottleneck in the execution | E. |
all the above. |
Answer: Option E
Explanation:
|
28. |
The salient feature of functional organisation is |
A. |
strict adherence to specifications | B. |
separation of planning and design part | C. |
each individual maintains functional efficiency | D. |
work is properly planned and distributed | E. |
all the above. |
Answer: Option E
Explanation:
|
29. |
Critical path method |
A. |
is an improvement upon bar chart method | B. |
provides a realistic approach to daily problems | C. |
avoids delays which are very common in bar charts | D. |
was invented by Morgan R. Walker of Dupot and James E. Kalley or Remington U.S.A. in 1957 | E. |
All the above. |
Answer: Option E
Explanation:
|
30. |
CPM is |
A. |
synthesising in concepts | B. |
is built of activities oriented programme | C. |
is based on time estimate | D. |
is used for repetitive works | E. |
all the above. |
Answer: Option E
Explanation:
|