Civil Engineering - Construction Management

Exercise : Construction Management - Section 2
1.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
Answer: Option
Explanation:
No answer description is available. Let's discuss.

2.
Pick up the correct statement from the following:
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
Latest occurrence time is taken as contractual obligation time
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

3.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
1
2
3
4
Answer: Option
Explanation:
No answer description is available. Let's discuss.

4.
For the execution of a project, a contractor is
a person
a firm
an agency
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

5.
Railway projects are treated as
light construction
heavy construction
industrial construction
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.