6. 

Pick up the correct statement from the following:

A. Optimistic time estimate refers to activities
B. Pessimistic time estimate refers to activities
C. Most likely time estimate refers to activities
D. Expected time estimate refers to activities
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

7. 

The critical activity has

A. maximum float
B. minimum float
C. zero float
D. none of these.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

8. 

The main disadvantage of line organisation, is

A. rigid structure
B. extraordinary delay in communications
C. top level executions over work
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

9. 

Pick up the correct statement from the following:

A. The difference of latest occurence time and earliest expected time, is called slack
B. The activities connecting the events having zero slack, lie on the critical path
C. The critical path consumes the maximum time
D. All the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

10. 

Pre-tender stage requires

A. acquisition of land
B. selection of site
C. formalisation of alignment of work
D. formalisation of designs and preparation of estimate
E. all the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.