9.
Pick up the correct statement from the following:
The difference of latest occurence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Romi said:   6 years ago
Critical path.

It is the sequence of critical activities, which decide the total project duration. A critical path consumes maximum resources. It is the longest path and consumes maximum time. It is the one, which connects the events having zero minimum float.