Civil Engineering - Construction Management

Exercise : Construction Management - Section 2
31.
Pick up the correct statement from the following:
Programme Evaluation and Review Technique, is event oriented
Programme Evaluation and Review Technique is not event oriented
Critical Path Method is event oriented
Critical Path method is event oriented.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

32.
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
19
14
24
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

33.
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
20
25
35
15
Answer: Option
Explanation:
No answer description is available. Let's discuss.

34.
While filling the tender for any work, the contractor considers
site survey
availability of construction materials
availability of labour
study of specifications
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.