Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 31)
31.
Pick up the correct statement from the following:
Programme Evaluation and Review Technique, is event oriented
Programme Evaluation and Review Technique is not event oriented
Critical Path Method is event oriented
Critical Path method is event oriented.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

WASEEM SANGI said:   3 years ago
PERT : Event-oriented.

CPM : Activity oriented.

OPSC AEE said:   6 years ago
PERT :-

Event Oriented.
Probabilistic approach.
Suitable for new project.
1950.
Beta Curve.

CPM :-

Activity oriented.
Deterministic approach.
Suitable for repetative work.
1957.
Normal distribution curve.
(1)

HARDIK said:   6 years ago
PERT is event orinated.

CPM is Activity orinated.

Chitra said:   6 years ago
Option C & D is same please explain the correct answer.