11. 

The final selection of a construction site, is done by

A. departmental representative or user
B. local civil authority representative
C. representative of engineer authority
D. representative of administration
E. all the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

12. 

Pick up the correct statement from the following:

A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The float which affects neither the processor nor the successor activities, is called independent float
D. The difference between total float and free float, is called interfering float
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

13. 

The first stage of a construction, is

A. preparation of estimate
B. survey of the site
C. initiation of proposal
D. preparation of tender
E. allotment of funds.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

14. 

PERT is

A. an analytic in concept
B. limited of event oriented diagrams
C. used for research and development projects
D. based on three time estimates for activities linking up two events
E. all the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

15. 

Residential buildings are treated as

A. light construction
B. heavy construction
C. industrial construction
D. private construction.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.