Civil Engineering - Construction Management

Exercise :: Construction Management - Section 2

16. 

The main advantage of line organisation, is :

A. effective command and control
B. defined responsibilities at all levels
C. rigid discipline in the organisation
D. ability of quick decision at all levels
E. all the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

17. 

PERT analysis is based on

A. optimistic time
B. pessimistic time
C. most likely time
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

18. 

For completion of a project, the critical path of the network represents

A. minimum time
B. maximum time
C. maximum cost
D. minimum cost.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

19. 

In CPM analysis,

A. emphasis is given to activities
B. uncertainties are not allowed
C. activities are represented by arrows
D. beginning and end of an activity, are denoted by nodes
E. all the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

20. 

A goiden rule for the procurement of construction stones, suggests

A. 100% at the site
B. 67% at the site and 33% under procurement
C. 50% at the site and 50% under procurement
D. 33% at the site and 67% under procurement
E. none of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.