20. 

A goiden rule for the procurement of construction stones, suggests

[A]. 100% at the site
[B]. 67% at the site and 33% under procurement
[C]. 50% at the site and 50% under procurement
[D]. 33% at the site and 67% under procurement
[E]. none of these.

Answer: Option B

Explanation:

No answer description available for this question.

Priyanka Shah said: (Jul 16, 2019)  
Please explain the answer.

Haroon said: (Sep 2, 2019)  
Procurement of materials for a construction site is about (2/3rd) of material stored at the site itself and (1/3rd) of material is procured somewhere else.

Opsc Aee said: (Oct 26, 2019)  
70% material must be available at site, rest 30% we can procure. If it imbalanced then cost of the project and completion of the project will directly affect.

Its can vary for building construction but the rule must follow in road construction.