Discussion :: Construction Management - Section 2 (Q.No.3)

3. 

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

[A]. 1
[B]. 2
[C]. 3
[D]. 4

Answer: Option A

Explanation:

No answer description available for this question.

Sume said: (Nov 25, 2015)  
That is reinforced cement concrete.

Sufajo said: (Jul 17, 2018)  
But some item in DSR, formwork exclude.

Denny said: (Aug 9, 2018)  
1 bar for supplying of a material.

Rohit said: (Dec 4, 2019)  
Everyone consumes time so there will be 5 bars.

Ali said: (Dec 31, 2019)  
It depends, 1 is not an absolute answer.

Guriya said: (Mar 7, 2020)  
1 is absolutely correct answer because, the overall work is concrete work i.e. materials for concrete, formwork reinforcing, removal of formwork and curing of concrete so all the works are concrete work so option A is correct one.

Dipu Bunku Rose said: (Mar 8, 2020)  
Given answer is wrong. It should be 5. Total 5 activities.

Sankar said: (May 16, 2020)  
Right. Thanks@Dipu Bhuku rose.

Harsh said: (Jul 16, 2020)  
Right @Guriya.

The correct option is 1, Since everything is related to concreting work.

Sagar Meghani said: (Sep 24, 2020)  
@Dipu.

Here is a bar chart & we know that the bar chart is didn't shown the sub-critical activities.

Lolla Odeh said: (Oct 31, 2020)  
I think the correct answer is 4 cause we have 4 activity each activity need some times to do it.