3.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
1
2
3
4
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 1 of 2.

MUHAMMAD NABI said:   3 years ago
Concrete work is an activity.

And, The various functions under each activity are shown by one bar on a bar chart.

So, Concrete work is an activity and others are functions.

So, No of bars will be 1.
(7)

Lolla odeh said:   5 years ago
I think the correct answer is 4 cause we have 4 activity each activity need some times to do it.
(1)

Sagar Meghani said:   5 years ago
@Dipu.

Here is a bar chart & we know that the bar chart is didn't shown the sub-critical activities.

Harsh said:   5 years ago
Right @Guriya.

The correct option is 1, Since everything is related to concreting work.
(1)

Sankar said:   5 years ago
Right. Thanks@Dipu Bhuku rose.

Dipu bunku rose said:   5 years ago
Given answer is wrong. It should be 5. Total 5 activities.
(1)

Guriya said:   5 years ago
1 is absolutely correct answer because, the overall work is concrete work i.e. materials for concrete, formwork reinforcing, removal of formwork and curing of concrete so all the works are concrete work so option A is correct one.

Ali said:   6 years ago
It depends, 1 is not an absolute answer.

Rohit said:   6 years ago
Everyone consumes time so there will be 5 bars.

Denny said:   7 years ago
1 bar for supplying of a material.