Discussion :: Construction Management - Section 1 (Q.No.30)

30. 

CPM is

[A]. synthesising in concepts
[B]. is built of activities oriented programme
[C]. is based on time estimate
[D]. is used for repetitive works
[E]. all the above.

Answer: Option E

Explanation:

No answer description available for this question.

Amruta said: (May 15, 2014)  
It should be B.

Expl:repetitive work and time estimate it deals with PERT.

PERT is concerned with research where repetitive works are done and there are three time estimates in this while in CPM there duration is given.

Sarit said: (Feb 22, 2018)  
Yes, B is the correct one.

Devendra Mahatha said: (Feb 8, 2021)  
It should be B. I agree @Amruta.