CPM is
synthesising in concepts
is built of activities oriented programme
is based on time estimate
is used for repetitive works
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
3 comments Page 1 of 1.

Amruta said:   1 decade ago
It should be B.

Expl:repetitive work and time estimate it deals with PERT.

PERT is concerned with research where repetitive works are done and there are three time estimates in this while in CPM there duration is given.

Devendra Mahatha said:   5 years ago
It should be B. I agree @Amruta.

Sarit said:   8 years ago
Yes, B is the correct one.