Civil Engineering - Construction Management

Exercise :: Construction Management - Section 1

46. 

If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

47. 

The Overall in-charge of an organisation at the site responsible for the execution of the works, is

A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

48. 

Modular co-ordination of construction means proper

A. planning
B. designing
C. execution
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

49. 

Pick up the correct statement from the following:

A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. CPM does not make any allowance for the uncertainties in the duration of time
D. In CPM, the time is related to cost
E. All the above.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.