Pick up the correct statement from the following:

[A]. CPM analysis is activity oriented
[B]. PERT analysis is event oriented
[C]. CPM does not make any allowance for the uncertainties in the duration of time
[D]. In CPM, the time is related to cost
[E]. All the above.

Answer: Option E

Explanation:

No answer description available for this question.

Rishu Raj said: (Mar 23, 2018)  
How is option D possible? Please explain.

Befkadu said: (May 11, 2018)  
Thank you all for explaining this.

Kalloljit said: (Oct 9, 2020)  
D is not correct. PERT considers Time as directly proportional to cost.

Pawan said: (Aug 26, 2021)  
How is option D is possible? Please explain clearly.