Pick up the correct statement from the following:
CPM analysis is activity oriented
PERT analysis is event oriented
CPM does not make any allowance for the uncertainties in the duration of time
In CPM, the time is related to cost
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Pawan said:   3 years ago
How is option D is possible? Please explain clearly.

Kalloljit said:   4 years ago
D is not correct. PERT considers Time as directly proportional to cost.

Befkadu said:   7 years ago
Thank you all for explaining this.

Rishu Raj said:   7 years ago
How is option D possible? Please explain.