Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 49)
49.
Pick up the correct statement from the following:
CPM analysis is activity oriented
PERT analysis is event oriented
CPM does not make any allowance for the uncertainties in the duration of time
In CPM, the time is related to cost
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Rishu Raj said:   7 years ago
How is option D possible? Please explain.

Befkadu said:   6 years ago
Thank you all for explaining this.

Kalloljit said:   4 years ago
D is not correct. PERT considers Time as directly proportional to cost.

Pawan said:   3 years ago
How is option D is possible? Please explain clearly.

Post your comments here:

Your comments will be displayed after verification.