41.
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
started 5 days later
completed 5 days later
performed at slower rate in 15 days
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

42.
Works costing less than Rs. 20,000 are treated as
projects
major projects
minor projects
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

43.
A critical ratio scheduling
establishes the relative priorities among various activities on a common basis
determines the status of each activity
adjusts automatically changes in activity progress
is a dynamic system
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

44.
Bar charts are suitable for
minor works
major works
large projects
all the Above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

45.
The first method invented for planning projects, was
Bar chart method
Milestone chart
Critical path method (CPM)
Programme Evaluation and Review Technique (PERT)
Answer: Option
Explanation:
No answer description is available. Let's discuss.