Civil Engineering - Construction Management

Exercise :: Construction Management - Section 1

41. 

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

42. 

Works costing less than Rs. 20,000 are treated as

A. projects
B. major projects
C. minor projects
D. all the above.

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

43. 

A critical ratio scheduling

A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of these.

Answer: Option E

Explanation:

No answer description available for this question. Let us discuss.

44. 

Bar charts are suitable for

A. minor works
B. major works
C. large projects
D. all the Above.

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

45. 

The first method invented for planning projects, was

A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.