Civil Engineering - Construction Management
Exercise :: Construction Management - Section 1
41. |
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be |
A. |
started 5 days later | B. |
completed 5 days later | C. |
performed at slower rate in 15 days | D. |
all the above. |
Answer: Option D
Explanation:
|
42. |
Works costing less than Rs. 20,000 are treated as |
A. |
projects | B. |
major projects | C. |
minor projects | D. |
all the above. |
Answer: Option C
Explanation:
|
43. |
A critical ratio scheduling |
A. |
establishes the relative priorities among various activities on a common basis | B. |
determines the status of each activity | C. |
adjusts automatically changes in activity progress | D. |
is a dynamic system | E. |
none of these. |
Answer: Option E
Explanation:
|
44. |
Bar charts are suitable for |
A. |
minor works | B. |
major works | C. |
large projects | D. |
all the Above. |
Answer: Option A
Explanation:
|
45. |
The first method invented for planning projects, was |
A. |
Bar chart method | B. |
Milestone chart | C. |
Critical path method (CPM) | D. |
Programme Evaluation and Review Technique (PERT) |
Answer: Option A
Explanation:
|