Discussion :: Construction Management - Section 1 (Q.No.45)

45. 

The first method invented for planning projects, was

[A]. Bar chart method
[B]. Milestone chart
[C]. Critical path method (CPM)
[D]. Programme Evaluation and Review Technique (PERT)

Answer: Option A

Explanation:

No answer description available for this question.

Anushka Patil said: (Feb 13, 2017)  
Bar chart method - 1900.
Milestone chart -1940.
CPM - 1957.

Yugareddy said: (Mar 23, 2019)  
What about PERT?

Obaid Khattak said: (Apr 29, 2019)  
PERT 1950.