Civil Engineering - Construction Management - Discussion

Discussion :: Construction Management - Section 1 (Q.No.41)

41. 

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

[A]. started 5 days later
[B]. completed 5 days later
[C]. performed at slower rate in 15 days
[D]. all the above.

Answer: Option D

Explanation:

No answer description available for this question.

Tinku said: (Dec 5, 2016)  
Please explain this clearly.

Dvd said: (Aug 2, 2017)  
Total float = LFT-EFT=LST-EST.

Abhishek Roy said: (Nov 3, 2017)  
Total float = LFT - EST - DURATION.

Priyakarthik said: (Apr 30, 2018)  
Not understand the solution. Please explain in detail.

Loai said: (Jun 27, 2018)  
Let's say that we have two activities A, and B. However, activity A has 10 days duration that means " without considering the float "activity A has 10 days to complete and must start on time to finish within its duration 10 days.

Now, with Total float, activity A has 5 days before starting this means "activity A still has extra time to start late. Because this will not affect the completion date since we talk about " Total float " Not Free Float " so option A is correct. Accordingly, starting 5 days late this will result in complete after 15 days " 10+5 days" this will lead to option C which is correct as well. Finally, activity A has 10 days +5 days this means, in case A started after 10 days. You still have 5 days to complete on time. Which lead to Option B.

Amit said: (Oct 24, 2018)  
Let's say that we have two activities A, and B.

However, activity A has 10 days duration that means " without considering the float "activity A has 10 days to complete and must start on time to finish within its duration 10 days.

Now, with Total float, activity A has 5 days before starting this means "activity A still has extra time to start late. Because this will not affect the completion date since we talk about " Total float " Not Free Float " so option A is correct. Accordingly, starting 5 days late this will result in complete after 15 days " 10+5 days" this will lead to option C which is correct as well. Finally, activity A has 10 days +5 days this means, in case A started after 10 days. You still have 5 days to complete on time. Which lead to Option B.

Abhishek said: (May 28, 2019)  
Total float is the amount of time of an activity which doesn't affect the estimated completion of the period of activity.

Here 10 days are available for completion of an activity.

The total float is 5 days. Means in 10 days 5 days can be a delay which doesn't affect the completion time of activity.

Here answer will be started 5 days later.

Abhi said: (May 28, 2019)  
@Amit @Loai.

Total float means the time that can be a delay which doesn't affect the estimated completion duration.

Pawan said: (Jun 17, 2019)  
Thanks for explaining @Loai.

Umair Ahmad said: (May 29, 2021)  
I think both option A and C are correct.

Post your comments here: