Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 41)
41.
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
started 5 days later
completed 5 days later
performed at slower rate in 15 days
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
10 comments Page 1 of 1.

Amit said:   7 years ago
Let's say that we have two activities A, and B.

However, activity A has 10 days duration that means " without considering the float "activity A has 10 days to complete and must start on time to finish within its duration 10 days.

Now, with Total float, activity A has 5 days before starting this means "activity A still has extra time to start late. Because this will not affect the completion date since we talk about " Total float " Not Free Float " so option A is correct. Accordingly, starting 5 days late this will result in complete after 15 days " 10+5 days" this will lead to option C which is correct as well. Finally, activity A has 10 days +5 days this means, in case A started after 10 days. You still have 5 days to complete on time. Which lead to Option B.

Loai said:   7 years ago
Let's say that we have two activities A, and B. However, activity A has 10 days duration that means " without considering the float "activity A has 10 days to complete and must start on time to finish within its duration 10 days.

Now, with Total float, activity A has 5 days before starting this means "activity A still has extra time to start late. Because this will not affect the completion date since we talk about " Total float " Not Free Float " so option A is correct. Accordingly, starting 5 days late this will result in complete after 15 days " 10+5 days" this will lead to option C which is correct as well. Finally, activity A has 10 days +5 days this means, in case A started after 10 days. You still have 5 days to complete on time. Which lead to Option B.
(1)

Abhishek said:   6 years ago
Total float is the amount of time of an activity which doesn't affect the estimated completion of the period of activity.

Here 10 days are available for completion of an activity.

The total float is 5 days. Means in 10 days 5 days can be a delay which doesn't affect the completion time of activity.

Here answer will be started 5 days later.
(1)

Abhi said:   6 years ago
@Amit @Loai.

Total float means the time that can be a delay which doesn't affect the estimated completion duration.

Priyakarthik said:   7 years ago
Not understand the solution. Please explain in detail.

Umair Ahmad said:   4 years ago
I think both option A and C are correct.

Abhishek Roy said:   8 years ago
Total float = LFT - EST - DURATION.

DVD said:   8 years ago
Total float = LFT-EFT=LST-EST.

Tinku said:   9 years ago
Please explain this clearly.

PAWAN said:   6 years ago
Thanks for explaining @Loai.