Civil Engineering - Construction Management
Exercise :: Construction Management - Section 1
36. |
An Executive Engineer may have powers upto |
A. |
Rs. 25,000 | B. |
Rs. 50,000 | C. |
Rs. 100,000 | D. |
Rs. 200,000 | E. |
Rs. 500,000 |
Answer: Option A
Explanation:
|
37. |
The main principle of an organisation, is |
A. |
unity of command | B. |
cohegency | C. |
effective control at all levels | D. |
delegation of authority | E. |
all the above. |
Answer: Option E
Explanation:
|
38. |
The estimated time required to perform an activity, is known as |
Answer: Option C
Explanation:
|
39. |
A CPM family includes |
A. |
CPA (Critical Path Analysis) | B. |
CPP (Critical Path Plotted) | C. |
MCE (Minimum Cost Expenditure) | D. |
CPS (Critical Path Scheduling) | E. |
All the above. |
Answer: Option E
Explanation:
|
40. |
The time which results in the leasi, possible construction cost of an activity, is known |
A. |
normal time | B. |
slow time | C. |
crash time | D. |
standard time. |
Answer: Option B