31.
Critical path lies along the activities having total float
positive
negative
zero
same.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

32.
Construction team means
an engineer
an architect
an owner
a contractor
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

33.
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
1. Pouring of Concrete
2. Erection of form work
3. Curing of concrete
4. Removal of form work
1. Erection of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work
1. Removal of form work
2. Erection of form work
3. Pouring of concrete
4. Curing of concrete
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work
Answer: Option
Explanation:
No answer description is available. Let's discuss.

34.
A construction schedule is prepared after collecting
number of operations
output of labour
output of machinery
quantity of various items
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

35.
Site order book is used for recording
instructions by the executive engineers
construction measurements
issue of store equipments
names of the casual labour.
Answer: Option
Explanation:
No answer description is available. Let's discuss.