Civil Engineering - Construction Management - Discussion

Discussion :: Construction Management - Section 1 (Q.No.33)

33. 

Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:

[A]. 1. Pouring of Concrete
2. Erection of form work
3. Curing of concrete
4. Removal of form work
[B]. 1. Erection of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work
[C]. 1. Removal of form work
2. Erection of form work
3. Pouring of concrete
4. Curing of concrete
[D]. 1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work

Answer: Option B

Explanation:

No answer description available for this question.

Patrick said: (Aug 21, 2017)  
The correct pattern should be

1. Erection of form work
2. Pouring concrete
3. Removal of form work
4. Curing of concrete.

Prangit Bhardwaj said: (May 17, 2018)  
Curing is the last step, so the pattern should be B) 1243.

Mohan Priyank said: (Sep 2, 2019)  
Curing may be the last step, but unless you don't remove formwork you cannot do the activity no. 4.

I agree @Patrick.

So, the correct sequence would be 1234.

Yet said: (Aug 24, 2020)  
It differs as the structure varies.

In Case of slab, removal of formwork is after curing while in column curing is after removal of formwork.