Discussion :: Construction Management - Section 1 (Q.No.33)
Patrick said: (Aug 21, 2017) | |
The correct pattern should be 1. Erection of form work 2. Pouring concrete 3. Removal of form work 4. Curing of concrete. |
Prangit Bhardwaj said: (May 17, 2018) | |
Curing is the last step, so the pattern should be B) 1243. |
Mohan Priyank said: (Sep 2, 2019) | |
Curing may be the last step, but unless you don't remove formwork you cannot do the activity no. 4. I agree @Patrick. So, the correct sequence would be 1234. |
Yet said: (Aug 24, 2020) | |
It differs as the structure varies. In Case of slab, removal of formwork is after curing while in column curing is after removal of formwork. |