Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 33)
33.
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
Discussion:
4 comments Page 1 of 1.
Patrick said:
8 years ago
The correct pattern should be
1. Erection of form work
2. Pouring concrete
3. Removal of form work
4. Curing of concrete.
1. Erection of form work
2. Pouring concrete
3. Removal of form work
4. Curing of concrete.
Prangit Bhardwaj said:
7 years ago
Curing is the last step, so the pattern should be B) 1243.
(1)
Mohan Priyank said:
6 years ago
Curing may be the last step, but unless you don't remove formwork you cannot do the activity no. 4.
I agree @Patrick.
So, the correct sequence would be 1234.
I agree @Patrick.
So, the correct sequence would be 1234.
Yet said:
5 years ago
It differs as the structure varies.
In Case of slab, removal of formwork is after curing while in column curing is after removal of formwork.
In Case of slab, removal of formwork is after curing while in column curing is after removal of formwork.