Civil Engineering - Construction Management - Discussion

Discussion :: Construction Management - Section 1 (Q.No.31)

31. 

Critical path lies along the activities having total float

[A]. positive
[B]. negative
[C]. zero
[D]. same.

Answer: Option C

Explanation:

No answer description available for this question.

Rohit said: (Dec 4, 2019)  
Why not - ve, as it's given the first priority wrt to 0.

Post your comments here: