Discussion Forum : Construction Management - Section 1 (Q.No. 46)
46.
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
Discussion:
7 comments Page 1 of 1.
Anees said:
3 years ago
Float of predecessor activity becomes slack of successor activity.
Yash jain said:
4 years ago
Time least(TL) for an activity. @Hamza.
Hamza said:
5 years ago
What is TL here?
Romi said:
6 years ago
Late start - early start.
Late finish - early finish.
Latest allowable event - early finish.
Total slck can be + or -ve.
Total slack is the amount of time the whole project can be delayed without pushing the end date of the project. This is calculated by using early and late starts and early and late finishes for tasks. Total slack is calculated as the smaller value of the late finish minus the early finish when compared to early start minus the late start.
Late finish - early finish.
Latest allowable event - early finish.
Total slck can be + or -ve.
Total slack is the amount of time the whole project can be delayed without pushing the end date of the project. This is calculated by using early and late starts and early and late finishes for tasks. Total slack is calculated as the smaller value of the late finish minus the early finish when compared to early start minus the late start.
(2)
FAWAZ said:
6 years ago
LST/LAST START TIME.
EST/EARLIEST START TIME.
LFT/LAST FINISH TIME.
EFT/EARLIEST FINISH TIME.
EST/EARLIEST START TIME.
LFT/LAST FINISH TIME.
EFT/EARLIEST FINISH TIME.
Adarsha said:
7 years ago
Latest allowable event occurance time=Latest Finish Time.
HAR said:
7 years ago
LST=LATEST FINISH TIME.
EST=EARLIEST FINISH TIME.
LFT=LATEST FINISH TIME.
EFT=EARLIEST FINISH TIME.
EST=EARLIEST FINISH TIME.
LFT=LATEST FINISH TIME.
EFT=EARLIEST FINISH TIME.