26.
The difference between the time avail-to do a job and the time required to do the job, is known as
Discussion:
2 comments Page 1 of 1.
Dhaffod said:
7 years ago
Float =Time availed - Time Required.
Float shows the time within which you can delay an activity without affecting the overall duration of a project.
Float shows the time within which you can delay an activity without affecting the overall duration of a project.