Civil Engineering - Construction Management - Discussion

Discussion :: Construction Management - Section 1 (Q.No.9)

9. 

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

[A]. EF = ES + D
[B]. LS = LF - D
[C]. LF = LS + D
[D]. D = EF - ES
[E]. all the above.

Answer: Option E

Explanation:

No answer description available for this question.

Joy said: (Jan 11, 2020)  
Explain the answer.

Nirash Nirban said: (Sep 7, 2020)  
Explain the given answer.

Salman said: (Oct 6, 2020)  
Duration, D=Early finish- early start or D = LF - LS.
Option A is same to D.
B and C are same.
So E is the correct answer.