6.
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
7.
In the given figure, the network of a project represents


8.
Pick up the PERT event from the following:
9.
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
10.
Final technical authority of a project lies with