The performance of a specific task in CPM, is known
Dummy
Event
Activity
Contract.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

12.
Pick up the correct statement from the following:
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

13.
A Milestone chart
shows the interdependencies of various jobs
depicts the delay of jobs, if any
points outgoing ahead of schedule of jobs, if any
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

14.
Completion of an activity on CPM network diagram, is generally known
Event
Node
Connector
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

15.
A dummy activity
is artificially introduced
is represented by a dotted line
does not consume time
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.