Civil Engineering - Construction Management
Exercise :: Construction Management - Section 1
11. |
The performance of a specific task in CPM, is known |
Answer: Option C
Explanation:
|
12. |
Pick up the correct statement from the following: |
A. |
The float may be positive, zero or negative | B. |
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed | C. |
If the float of an activity is negative, delay in its performance is bound to delay the completion of project | D. |
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project | E. |
All the above. |
Answer: Option E
Explanation:
|
13. |
A Milestone chart |
A. |
shows the interdependencies of various jobs | B. |
depicts the delay of jobs, if any | C. |
points outgoing ahead of schedule of jobs, if any | D. |
none of these. |
Answer: Option D
Explanation:
|
14. |
Completion of an activity on CPM network diagram, is generally known |
A. |
Event | B. |
Node | C. |
Connector | D. |
All the above. |
Answer: Option D
Explanation:
|
15. |
A dummy activity |
A. |
is artificially introduced | B. |
is represented by a dotted line | C. |
does not consume time | D. |
all the above. |
Answer: Option D
Explanation:
|