11. 

The performance of a specific task in CPM, is known

[A]. Dummy
[B]. Event
[C]. Activity
[D]. Contract.

Answer: Option C

Explanation:

No answer description available for this question.

Lal Babu Yadav said: (Feb 11, 2015)  
CPM is the activity oriented.

Hesham Bendary said: (Apr 16, 2015)  
CPM : Critical Path Method.

Har said: (Aug 30, 2017)  
A PERT chart is a project management tool used to schedule, organize, and coordinate tasks within a project. PERT stands for Program Evaluation Review Technique, a methodology developed by the US Navy in the 1950s to manage the Polaris submarine missile program. A similar methodology, the Critical Path Method (CPM) was developed for project management in the private sector at about the same time.

The performance of a specific task in PERT, is known EVENT.

Awais Ali said: (Jul 8, 2020)  
Event is the right answer.

Gurjant Singh said: (Sep 4, 2020)  
Yes, event is the right answer.

Sahil Chavda said: (Dec 12, 2020)  
Given options is correct.

Sajid Aziz said: (Dec 29, 2020)  
The beginning and end of a job, are called events.

The performance of the specific task in CPM is called activity.