14. 

Completion of an activity on CPM network diagram, is generally known

[A]. Event
[B]. Node
[C]. Connector
[D]. All the above.

Answer: Option D

Explanation:

No answer description available for this question.

J Singh said: (Jul 26, 2018)  
What is node?

Ganesh Guwar said: (Jun 6, 2020)  
@J Singh.

The activity which consumes minimum time is called nodes.

Yash Banode said: (Oct 16, 2020)  
Occurrence of an Event is represented by a Node. So roughly they mean the same.