Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 14)
14.
Completion of an activity on CPM network diagram, is generally known
Event
Node
Connector
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

B Thapa said:   7 months ago
How the answer to that question could contain a "connector"? Please explain the answer.

Yash banode said:   4 years ago
Occurrence of an Event is represented by a Node. So roughly they mean the same.

Ganesh Guwar said:   4 years ago
@J Singh.

The activity which consumes minimum time is called nodes.

J Singh said:   6 years ago
What is node?

Post your comments here: