A dummy activity

[A]. is artificially introduced
[B]. is represented by a dotted line
[C]. does not consume time
[D]. all the above.

Answer: Option D

Explanation:

No answer description available for this question.

Varsha Gaikwad said: (Apr 23, 2020)  
Please explain in broad.

Umair Ahmad said: (May 29, 2021)  
A Dummy activity is a type of operation in a project network that neither requires any time nor any resource. It is an imaginary activity shown in a project network to identify the dependence among operations.

Umair Ahmad said: (May 29, 2021)  
Dummy activity may be critical or noncritical.

Yoseph said: (Oct 18, 2021)  
Dummy activity is non-critical activity.