A dummy activity
is artificially introduced
is represented by a dotted line
does not consume time
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Varsha Gaikwad said:   3 years ago
Please explain in broad.

Umair Ahmad said:   2 years ago
A Dummy activity is a type of operation in a project network that neither requires any time nor any resource. It is an imaginary activity shown in a project network to identify the dependence among operations.

Umair Ahmad said:   2 years ago
Dummy activity may be critical or noncritical.

Yoseph said:   1 year ago
Dummy activity is non-critical activity.