Civil Engineering - Construction Management
Exercise :: Construction Management - Section 1
16. |
Military organisation is known as |
A. |
line organisation | B. |
line and staff organisation | C. |
functional organisation | D. |
none of these. |
Answer: Option A
Explanation:
|
17. |
Pick up the incorrect statement from the following: |
A. |
The activity is the time consuming part of a project | B. |
The beginning and end of a job, are called events | C. |
The activity which consumes maximum time, is called a node | D. |
Logically and sequentially connected activities and events form a network | E. |
None of these. |
Answer: Option C
Explanation:
|
18. |
Various activities of a project, are shown on bar charts by |
A. |
vertical lines | B. |
horizontal lines | C. |
dots | D. |
crosses. |
Answer: Option B
Explanation:
|
19. |
Time and progress chart of a construction, is also known as |
A. |
Bar chart | B. |
Gantt chart | C. |
Modified Mile stone chart | D. |
Critical path method chart | E. |
All the above. |
Answer: Option E
Explanation:
|
20. |
Critical Path Net Work helps an engineer |
A. |
to concentrate his attention on critical activities | B. |
to divert the resources from non-critical advanced activities to critical activities | C. |
to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project | D. |
all the above. |
Answer: Option D
Explanation:
|