Civil Engineering - Construction Management - Discussion

Discussion :: Construction Management - Section 1 (Q.No.18)

18. 

Various activities of a project, are shown on bar charts by

[A]. vertical lines
[B]. horizontal lines
[C]. dots
[D]. crosses.

Answer: Option B

Explanation:

No answer description available for this question.

Hardik Chauhan said: (Sep 12, 2017)  
In book of construction managemet activity of project show on hvartical line on bar chart.

Mahendher Reddy said: (Dec 27, 2017)  
What is mean by bar chart?

Murli Solanki said: (Feb 12, 2018)  
A is correct one.

Shainy said: (Jun 10, 2018)  
How it is? I thought it is vertical lines also.

Puspendu said: (Sep 9, 2018)  
A is the correct answer. I too agree.

Swathi. S. K said: (Nov 12, 2018)  
I agree with the given answer B.

The horizontal bar represent the various activities involved in a construction work. And the vertical bar represents the respective jobs to be performed. Hence B is correct.

Pawan Raut said: (Dec 30, 2018)  
A is the correct.

Vertical line - Activities Horizontal - Duration.

Hayat said: (Aug 15, 2019)  
Right @Pawan Raut.

Suraj Bhosale said: (Oct 4, 2019)  
In book vertical line represents various activities of project and horizontal line shows time.

Ashok Behera said: (Apr 15, 2020)  
Yes, A is correct.

Deeptikant Sharma said: (Jun 25, 2020)  
A vertical line shows activities and horizontal line shows time duration.

Umair Ahmad said: (May 29, 2021)  
First time developed by Henry Gantt around 1900 and is used to deal with complex activities.

The bar chart consists of two coordinates, the horizontal represents the time elapsed and the vertical represents the job or activities performed.