18.
Various activities of a project, are shown on bar charts by
vertical lines
horizontal lines
dots
crosses.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
16 comments Page 1 of 2.

Akram said:   1 year ago
Here it is not asking about the axis i.e Vertical or horizontal axis.

The answer is B, because horizontal lines are used in charts to show the activities.
(1)

Akram said:   1 year ago
Here in the options, it is asking about the lines, not the axis.

So, the Horizontal lines are used to show the activities.
(1)

WASEEM SANGI said:   3 years ago
In Bar charts, time is represented in x-direction & the y-axis represents the activities.
So, the correct answer will be A.
(7)

Muhammad Ali Khetran said:   3 years ago
Yes, B is the correct answer, I agreed.
(3)

Umair Ahmad said:   4 years ago
First time developed by Henry Gantt around 1900 and is used to deal with complex activities.

The bar chart consists of two coordinates, the horizontal represents the time elapsed and the vertical represents the job or activities performed.
(3)

Deeptikant sharma said:   5 years ago
A vertical line shows activities and horizontal line shows time duration.

Ashok Behera said:   5 years ago
Yes, A is correct.

Suraj bhosale said:   6 years ago
In book vertical line represents various activities of project and horizontal line shows time.

Hayat said:   6 years ago
Right @Pawan Raut.

Pawan Raut said:   7 years ago
A is the correct.

Vertical line - Activities Horizontal - Duration.