Discussion Forum : Construction Management - Section 1 (Q.No. 12)
12.
Pick up the correct statement from the following:
Discussion:
11 comments Page 1 of 2.
Jitendra said:
3 years ago
Which activity has negative float? Please explain.
Mansur Ali said:
4 years ago
Except for critical path, all other network paths have different completion time and if any path has more or less or equal time then the critical path, then that path is called +ve, -ve or = FLOAT.
Asif said:
4 years ago
Correct Answer is D.
Sajid said:
7 years ago
What is meant by float here? Explain.
Gaurav said:
7 years ago
All are correct, it is saying float can be any value, not particularly total float.
Bikash medhi said:
7 years ago
Float and slack are analogous, not totally same.
Floats are classified as;
1) Total float
2) Free float
3) Independent float
4) interfering float
So, I think option (c) is correct.
Floats are classified as;
1) Total float
2) Free float
3) Independent float
4) interfering float
So, I think option (c) is correct.
Adarsha said:
7 years ago
Negative float, also known as negative slack, is the amount of time beyond aproject's scheduled completion that a task within the project requires. Total float is the amount of time a task within a project can be delayed without endangering theproject deadline. Hence all the options are correct.
Navi said:
8 years ago
Option d is correct.
Float of an activity can never be negative.
Float of an activity can never be negative.
Sarathy said:
8 years ago
Can't get this. Anyone explain me.
(1)
Zankloony said:
8 years ago
How total float could be positive or negative? This is wrong.