Pick up the correct statement from the following:
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
11 comments Page 2 of 2.

Kiran said:   9 years ago
Option D should be the answer because the float is zero hence, it is critical.