If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
Discussion:
3 comments Page 1 of 1.
Salman said:
5 years ago
Duration, D=Early finish- early start or D = LF - LS.
Option A is same to D.
B and C are same.
So E is the correct answer.
Option A is same to D.
B and C are same.
So E is the correct answer.
(2)
Nirash nirban said:
5 years ago
Explain the given answer.
Joy said:
6 years ago
Explain the answer.