Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

[A]. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
[B]. Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
[C]. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
[D]. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
[E]. All the above.

Answer: Option E

Explanation:

No answer description available for this question.