Pick up the incorrect statement from the following:

[A]. The various functions under each activity, are shown by one bar on Bar Charts
[B]. Bar chart establishes the interdependency of one event on another
[C]. Only approximate percentage of the completed work is reported
[D]. None of these,

Answer: Option B

Explanation:

No answer description available for this question.

Santosh said: (Apr 20, 2019)  
C is also incorrect.

Report should be as per completed work not as per approximate %.

Kalloljit said: (Oct 9, 2020)  
I think A is also incorrect.