Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 28)
28.
Pick up the incorrect statement from the following:
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these,
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
2 comments Page 1 of 1.

Santosh said:   6 years ago
C is also incorrect.

Report should be as per completed work not as per approximate %.

Kalloljit said:   5 years ago
I think A is also incorrect.