Online Civil Engineering Test - Estimating and Costing Test

Instruction:

  • This is a FREE online test. Beware of scammers who ask for money to attend this test.
  • Total number of questions: 20.
  • Time allotted: 30 minutes.
  • Each question carries 1 mark; there are no negative marks.
  • DO NOT refresh the page.
  • All the best!

Marks : 2/20


Total number of questions
20
Number of answered questions
0
Number of unanswered questions
20
Test Review : View answers and explanation for this test.

1.
Pick up the item of work not included in the plinth area estimate
Wall thickness
Room area
Verandah area
W.C. area
Courtyard area.
Your Answer: Option
(Not Answered)
Correct Answer: Option

2.
The plinth area of a building not includes
area of the walls at the floor level
area of stair cover
internal shaft for sanitary installations up to 2 sq m. in area
lift and wall including landing
area of cantilevered porch.
Your Answer: Option
(Not Answered)
Correct Answer: Option

3.
Pick up the correct statement from the following:
The estimated value of the work excluding the amount for contigencies, work charged establishment, tool and plants, is called work value
The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost
The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval
The order of a competent authority sanctioning a properly detailed estimate of the cost of a work of construction or repair is called technical sanction
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

4.
If tensile stress of a steel rod of diameter D is 1400 kg/cm2 and bond stress is 6 kg/cm2, the required bond length of the rod is
30 D
40 D
50 D
53 D
59 D
Your Answer: Option
(Not Answered)
Correct Answer: Option

5.
The total length of a cranked bar through a distance (d) at 45° in case of a beam of effective length L, is
L + 0.42 d
L + 2 x 0.42 d
L - 0.42 d
L - 2 x 0.4 d
Your Answer: Option
(Not Answered)
Correct Answer: Option

6.
Cost of fittings and their fixing is specified for the following sanitary fittings
Water closets
Flushing pipes
Lavatary basins
Sinks
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

7.
As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
1.80 litres for 5 to 10 users
1.20 litres for 15 users
1.35 for 20 users
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

8.
The cross-sections for a highway is taken at
right angle to the centre line
30 metres apart
intermediate points having abrupt change in gradient
the starting end points of the curves
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

9.
Pick up the correct statement from the following:
The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

10.
Pick up the excavation where measurements are made in square metres for payment.
Ordinary cuttings up to 1 m
surface dressing up to 15 cm depths
Surface excavation up to 30 cm depths
Both (b) and (c)
Both (a) and (b)
Your Answer: Option
(Not Answered)
Correct Answer: Option

11.
The item of steel work which is measured in sq.m, is
Collapsible gates
Rolling shutters
Steel doors
Ventilators and glazing.
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

12.
According to Indian Standards Institute, the actual size of modular bricks is
23 cm x 11.5 cm x 7.5 cm
25 cm x 13 cm x 7.5 cm
19 cm x 9 cm x 9 cm
20 cm x 10 cm x 10 cm
Your Answer: Option
(Not Answered)
Correct Answer: Option

13.
The unit of measurement is per quintal for the following:
Collapsible gates with rails
Rolling shutters
Expanded metal wire netting
M.S. reinforcement of R.C.C. works.
Your Answer: Option
(Not Answered)
Correct Answer: Option

14.
The rate of an item of work depends on
Specifications of works
Specifications of materials
Proportion of mortar
Method of construction
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

15.
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
1.00 m3
1.25 m3
1.50 m3
1.75 m3
Your Answer: Option
(Not Answered)
Correct Answer: Option

16.
The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is
Rs. 400
Rs. 425
Rs. 450
Rs. 500
Your Answer: Option
(Not Answered)
Correct Answer: Option

17.
The value of 'B' of Indian type W.C. shown in the given figure is :
45 cm
50 cm
30 cm
25 cm
Your Answer: Option
(Not Answered)
Correct Answer: Option

18.
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended
100 mm
150 mm
200 mm
175 mm
Your Answer: Option
(Not Answered)
Correct Answer: Option

19.
Pick up the correct statement from the following:
If the bed level is above N.S.L. the canal is called fully in baking and the berms are designed as 3 d where d is full supply depth of water (F.S.D.)
Area of canal in cutting = BD + Sd2 where B = bed width, d = depth of cutting and S is the side slope
Area of the bank of canal = B1d1 + Sd2 where B1, d1 and S are the width of bank, height of the bank above N.S.L. and side slope respectively
If F.S.L. is above N.S.L the canal is called partly in cutting and partly in filling and berms are designed as 2d where d is full supply depth
All the above.
Your Answer: Option
(Not Answered)
Correct Answer: Option

20.
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
500 m3
1000 m3
1500 m3
2000 m3
Your Answer: Option
(Not Answered)
Correct Answer: Option

*** END OF THE TEST ***
Time Left: 00:29:56
Post your test result / feedback here: