28. 

The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

[A]. 1.00 m3
[B]. 1.25 m3
[C]. 1.50 m3
[D]. 1.75 m3

Answer: Option B

Explanation:

No answer description available for this question.

Bhupender said: (Dec 30, 2016)  
Yes, it is right.

Dan said: (Jun 4, 2018)  
How is it possible?

Sahil said: (Jun 11, 2018)  
How? please Explain.

Suhas Gotmare said: (Jan 2, 2019)  
Brickwork plinth 1.25m 3 per mason.

Superstructure 1m 3 per mason per day.

Kanti said: (Jun 6, 2019)  
According to me, it is .63 in (1:6) for brickwork in foundation and plinth.