1.
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.

2.
For the construction of buildings, the subheads of the estimate are
Earthwork, Concrete work, Brick work
Brickwork, Stone work, Roofing
Brickwork Flooring, Wood work, Steel work
Plastering or pointing, finishing, water supply and sanitary work
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

3.
The measurement is made for stone work in square metre in case of
Wall facing
Columns, lintels, copings
Building work
Dressed stones in Chajjas
(a) and (d) of the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

4.
The 'centre line method' is specially adopted for estimating
Circular buildings
Hexagonal buildings
Octagonal buildings
Other geometrical shaped buildings
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

5.
The value of 'A' of Indian type W.C. shown in the given figure is :
25 cm
30 cm
40 cm
45 cm
Answer: Option
Explanation:
No answer description is available. Let's discuss.