Civil Engineering - Estimating and Costing
Exercise :: Estimating and Costing - Section 2
1. |
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is |
A. |
0.90 m3 | B. |
0.94 m3 | C. |
0.98 m3 | D. |
1.00 m3 |
Answer: Option B
Explanation:
|
2. |
For the construction of buildings, the subheads of the estimate are |
A. |
Earthwork, Concrete work, Brick work | B. |
Brickwork, Stone work, Roofing | C. |
Brickwork Flooring, Wood work, Steel work | D. |
Plastering or pointing, finishing, water supply and sanitary work | E. |
All the above. |
Answer: Option E
Explanation:
|
3. |
The measurement is made for stone work in square metre in case of |
A. |
Wall facing | B. |
Columns, lintels, copings | C. |
Building work | D. |
Dressed stones in Chajjas | E. |
(a) and (d) of the above. |
Answer: Option E
Explanation:
|
4. |
The 'centre line method' is specially adopted for estimating |
A. |
Circular buildings | B. |
Hexagonal buildings | C. |
Octagonal buildings | D. |
Other geometrical shaped buildings | E. |
All the above. |
Answer: Option E
Explanation:
|
5. |
The value of 'A' of Indian type W.C. shown in the given figure is :
 |
Answer: Option B
Explanation:
|