For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
25 comments Page 1 of 3.

Birjan rokaya said:   10 months ago
Area =100 m^2.

Thickness = 4cm
= 0.04M
Volume = 100 * 0.04
= 4M^3
The Volume of cement = dry volume/sum of the ratio.
= 1.54/1+2+4
= 0.22 M^3
For 4 m^3 = 0.22*4.
= 0.88M^3.
So ,0.90m^3 is the right answer.
(2)

Pranjal Saikia said:   2 years ago
Area = 100 M2.
Thickness = 4 cm = 0.04m.
Volume = 100*0.04 = 4 M3.
Add 54% of Dry vol = 4+ 54/100 * 4 = 6.16 m3.
Cement = 1/7 *6.16 = 0.88 m3.
(17)

Deepak kumar said:   2 years ago
As per my knowledge, the Correct answer is 0.888 cum.
(4)

PRAMOD RAI said:   2 years ago
0.88 m^3 is the correct answer.
(4)

Rumit Raj said:   2 years ago
Yes, correct. Thanks everyone.
(2)

Sakshi said:   2 years ago
Qc = (1.65 * 100* 0.04)*1/7.
Qc = 0.94m^3.
(9)

MILI said:   3 years ago
@Raj.

Very well analysis. Thanks.
(5)

Smruti R said:   3 years ago
The volume of concrete= 100 * .04 = 4.
10% increase for the unevenness + 50% increase for dry volume =4*1.1*1.5 = 6.6cum,
Cement=6.6/(1+2+4).
(1)

Aman said:   3 years ago
The volume of wet concrete = 100*0.04 = 4.
Increased mortar by 65% in dry mortar.
The volume of dry mortar=4+0.65*4=6.6.

Now,
Cement QTY = 6.6/7 = 0.94ans.
(6)

Shiva khadka said:   3 years ago
100*0.04=4*1.54=6.16/7=0.88ans.

So, 0.90cum is the right answer.